At Bluewaters, the living room was the unfinished part
How much of the Bluewaters pipework was ready on 6 April 2026? That evening the answer depended on where you stood in the apartment. In the living room the fittings were still being reworked. Farther along, the pipework in the other rooms was ready.
2026-04
The crew put the living-room fittings at roughly halfway through rework. Halfway is a useful figure here only if it stays attached to the right room. Applying it to the whole apartment would have understated progress in one place and overstated it in another.

Valve handles above the ladder, between insulated pipe runs.
The question about the farther rooms
A follow-up about the rooms farther away brought a separate answer from the team. Their pipework was ready. A few insulation details still needed attention on the job, alongside the remaining living-room work.

Two capped branches below the horizontal run at Bluewaters.
A handover that simply said “pipework ongoing” would send the next person looking through the whole apartment. This one gave them a room to go to and a task to pick up there. The living-room fittings were the unfinished part.